Picking robot pilot checklist

A step-by-step checklist for a picking robot pilot: the data to pull, a fair baseline, site readiness, safety, and written success criteria.
Picking robot pilot checklist

A picking robot pilot is a limited trial of one method in one zone, measured against how you pick today. The 13-step checklist below covers the order data to export, a baseline measured over at least two normal weeks, site readiness, safety and consultation, and success criteria written down before any robot arrives.

You can tick the list off in your browser, and the sections under it give the reasoning behind each item. The aim is that when the pilot ends you can say with evidence whether to scale, change or stop, and that nobody can dispute the numbers because the method was agreed in advance.

The checklist works for any of the families on this site: collaborative mobile robots, goods-to-person systems and robot arms. Some steps matter more for one family than another, and the notes say where.

Picking robot pilot checklist

0 of 13 ticked

Why do picking pilots go wrong?

Pilots fail in predictable ways, and most of them are visible before the pilot begins.

The first is the missing baseline. If nobody measured the current pick rate and accuracy in the pilot zone, the result has nothing to be compared with, and the comparison falls back on an industry average or a supplier’s figure. The second is the flattering zone. A pilot placed in the tidiest aisle, with the easiest products, in a quiet month, produces numbers that fall apart when the system meets the full range at peak. The third is vague success. If the measures are agreed after the results arrive, they tend to be the ones that look good.

The fourth is hidden labour. A pilot that counts picker hours but not the time of the team leader, the person clearing exceptions and the staff doing extra sorting understates the cost of the new method. The fifth is rushed consultation: workers told about the pilot a week before it starts have no chance to contribute, and the pilot misses information that would have helped. The last is the lack of an exit. Without a written decision rule, a pilot that falls short turns into an extended pilot, and the extension absorbs time and goodwill.

Each item on the checklist guards against one of these.

What data should you pull before talking to vendors?

Start with your own data, before any supplier has a chance to frame the problem.

Export twelve months of order lines with order number, product, quantity, date and time. Twelve months captures seasons and peaks. From that you can work out lines per order and units per line by week, the number of distinct products picked, the lines per product, and the busiest hours and days.

Rank products by lines picked and mark the fast movers. A small share of products often accounts for most lines, and that share is the first thing a supplier will ask you about. Note also the products you would worry about: fragile, awkward, heavy, tiny, in loose bags or with variable packaging. You will want some of those in the pilot.

If your warehouse management system cannot produce the export easily, ask your provider, and note the time it takes, because the same system will have to feed the robots. Data quality is itself a finding. If locations are inconsistent or timestamps are missing, fix them before automation, since robots follow the data they are given.

Use the calculator on the home page for a first estimate of picking hours, but only with rates you have measured.

How do you measure your current baseline fairly?

The baseline is the pick rate and accuracy of the current method in the pilot zone. Measure it with care, because everything later is compared with it.

Measure for at least two normal weeks, and longer if your volumes swing. Record lines picked per person-hour, using the hours pickers actually spend picking in that zone, and note how you separate picking from other tasks such as replenishment and cleaning. Record accuracy using the same audit method you will use in the pilot: a sample of orders checked at pack, claims and returns, or a full audit. Whatever method you choose, use it before and after.

Take the measurements at the same times of day and week as the pilot will run. If the pilot runs on day shift and the baseline comes from night shift, the comparison is invalid. Record also the conditions: staffing levels, the mix of orders, any unusual events. The aim is a baseline you would defend to a sceptical colleague.

Experience matters too. Pickers who know the zone and the products perform better than new starters, and a pilot staffed by your best people against a baseline set by the average team flatters the result. Keep staffing comparable, or record the difference.

Choosing the pilot zone and products

The pilot zone should represent the work you want the system to do, with some of the difficulty included.

Pick a zone with enough volume to give meaningful data in the pilot period, and with a mix of fast and slow movers. Include some awkward products. If the pilot involves a robot arm, include the products you suspect will be hard, with the packaging they come in. If it involves mobile robots, include the corner of the zone with the roughest floor and the narrowest aisle. A pilot that avoids the hard parts delays the discovery of them until the scale-up, where the discovery costs more.

Ease of installation is a fair consideration, but it should not decide the zone on its own. Be careful about the period too: a pilot run in a quiet month tells you little about peak. If you cannot run through a peak, ask the supplier to test at peak volume with simulated or recorded orders, and record that the pilot did not include real peak conditions.

Set the pilot length to produce enough data. A few days is rarely enough to see the spread between good and bad days, and several weeks is more informative. The length you choose should be written with the success criteria.

Site readiness: floors, Wi-Fi, power and fire services

Site readiness covers the practical matters that stall pilots.

Floors. Map the pilot zone. Note aisle widths, floor condition, slopes, joins, drains, door thresholds and any transitions between areas. Ask the supplier what tolerances the equipment needs, and test them. This step matters most for mobile robots and goods-to-person floors.

Wi-Fi. Survey coverage across the pilot zone, including between racks and in corners. Ask the supplier for the minimum signal and latency they need, and have your IT team or a network specialist measure it. Do the survey while the warehouse is operating, since equipment and stock affect signal.

Power and charging. Confirm charging locations and power with a licensed electrician. Plan where robots charge, how they queue and how charging fits around the peak. Ask your insurer whether conditions apply to battery charging, and include chargers in the risk assessment.

Fire services. For dense storage systems, fire protection is a design question for a fire safety engineer and the building surveyor. A pilot that adds fixed structure can raise questions that a mobile robot trial does not, so ask early.

Space. Allow for chargers, spare robots, a maintenance bay, a place for exceptions and a place for the supplier’s equipment during setup.

Integration scope with your warehouse management system

Robots follow instructions, and the instructions come from your systems. Settle the integration scope before the pilot starts.

Ask what the supplier needs: how orders are released, how locations are identified, how pick confirmations return, how inventory updates after each pick, and how short picks, cancellations and priority changes are handled. Ask your management system provider what they will do and what it will cost in time. Agree test cases in writing: a normal order, a short pick, a cancelled order, a priority order, a robot fault mid-order and a loss of connection.

Decide whether the pilot uses a full integration or a reduced one, such as a manual release of orders. A reduced integration is quicker to set up, and its results may not reflect live operation, so record the difference. If the pilot succeeds, the integration for scale-up should be scoped from what you learned.

Risk assessment and worker consultation before go-live

Before anything moves on the floor, complete a risk assessment and consult workers and their health and safety representatives.

Work health and safety law expects a business to manage risks using the hierarchy of controls, where elimination ranks highest and personal protective equipment lowest, and to consult workers on changes that may affect health and safety. Your state’s regulator publishes guidance, and a qualified safety professional can carry out the assessment. For mobile robots, ask the supplier which standards the system is designed to, including AS 5144.4 for driverless industrial trucks, and ask for the documents. The safety and staff questions page goes into the detail.

Consultation also improves the pilot. Pickers know where the floor is rough, where pallets are left and where products behave badly. Invite them to the layout review, tell them what is being measured and why, and say how their feedback will be recorded. Check your enterprise agreement or award for consultation steps beyond the legal minimum, and the Fair Work Ombudsman can direct you to the right information.

Success criteria agreed in writing

Write the success criteria before the pilot, share them with the supplier and have both sides acknowledge them.

Good criteria are measurable and tied to your baseline. Examples include the pick rate in lines per person-hour over the pilot period, accuracy measured by the same method as the baseline, robot availability, exceptions per hundred picks, the time to clear an exception, the labour used including support tasks, and any safety events or near misses. Each criterion should state the threshold, how it is measured, who records it and when.

Decide in advance how to treat the supplier’s own measures. A supplier may want to count a different rate, such as picks per hour at the robot and not per person-hour of all labour. Both numbers can be reported, and the decision should rest on the one you agreed. A supplier that insists on setting the measures alone is showing you how its results will be framed at the end.

Include criteria that are not about speed: how workers find the system, how often it needs attention, and whether the zone worked at peak. A pilot that raises the rate and leaves staff unable to cope with the faults has not succeeded.

Running the pilot: shifts, exceptions and logs

During the pilot, keep records as if someone will audit them.

Name who resolves robot errors on each shift and how fast, and write it into the roster. Keep a log of every stop, fault and exception: the time, the cause, who cleared it and how long it took. Keep the pick data in a form you can export. Review weekly with the supplier and the team, and note changes made to the system, because a result after three tweaks differs from a result on day one.

Watch for drift. Early enthusiasm and close supplier attention tend to produce good first weeks, and the question is what happens in week six when attention fades. Keep the same measurement method throughout. Record the shifts, the staffing and any unusual events. If the pilot runs into a peak, mark that period separately in the results.

Larger projects apply the same discipline at commissioning. Before Toll’s Sydney goods-to-person site went live in December 2017, the operator ran dry runs over 12 weeks, bringing 65 to 70 staff to the stations to pick air or pieces of paper so it could check throughput, accuracy and the links between systems, and it kept a conventional operation running next door while the automation was commissioned (Modern Materials Handling, 2019). A pilot is smaller, and the same habits apply: test before real orders depend on it, and keep a fallback.

Keep talking to pickers and team leaders during the pilot, and record what they say, including complaints that do not show up in the data.

How do you decide to scale, change or stop?

The decision rests on the criteria you wrote, applied to the data you collected.

If the criteria were met, scaling still needs a plan: the number of units, integration, building changes, training and a measure of whether the results hold at scale. If the criteria were met in some areas and not others, consider changing the scope, the products or the method. If they were not met, stopping is a legitimate outcome, and a pilot that saves you from a larger mistake has done its job.

Agree the exit terms with the supplier before you begin: what happens to the equipment, what you owe and what data you keep. Hold the decision meeting on the date you set, with the criteria, the data and the logs in front of everyone. The comparison of picking automation options is useful at this stage if the pilot suggests a different family would suit better. Questions about any step can be sent through the contact form.

Frequently asked questions

How long should a picking robot pilot run?

Long enough to show the spread between good and bad days, and ideally through some higher-volume days. A few days rarely suffices, and several weeks is more informative. Write the length down with the success criteria and note if real peak conditions were not covered.

Should the pilot use our busiest products?

Include them, and include awkward products too. A pilot built only from fast, easy items overstates the result. Choose a zone with a mix of velocities and some of the difficult products, and the roughest floor corner if mobile robots are involved.

Who should own the pilot inside the business?

One named person, usually in operations, with authority over the zone and the data, plus input from IT, safety and the team leaders. The owner holds the baseline, the criteria and the decision date, so that no single party controls the measures.

What baseline numbers should we record first?

Lines per person-hour in the pilot zone over at least two normal weeks, pick accuracy by your audit method, and the conditions: staffing, order mix and shifts. Record the time of support tasks too, so labour is counted in full before and after.

What if the vendor wants to choose the success measures?

Agree the measures yourself before the pilot, and let the vendor add their own as extra. If they insist on only their measures, it shows how results will be presented later. Write the thresholds, methods and recorders down and have both sides acknowledge them.

How do we involve pickers in the pilot?

Invite them to the layout review, explain what is measured and why, ask where floors and products cause trouble, and keep a log of their feedback during the trial. Consultation on changes that may affect health and safety is expected, so start before go-live.

What should happen if the pilot misses its targets?

Apply the decision rule you wrote: change the scope, products or method, or stop. Stopping is a legitimate result and a cheap one compared with scaling a mistake. Agree exit terms for equipment and data with the supplier before the pilot begins.