Collaborative picking robots: mobile robots that travel with pickers

How collaborative mobile robots carry totes between pickers and pack stations, what they need from your building, and how to measure the gain.
Collaborative picking robots: mobile robots that travel with pickers

A collaborative picking robot is an autonomous mobile robot (AMR) that carries totes through your existing aisles while people pick, so pickers walk less and the racking stays where it is. For safety standards, ISO 3691-4:2023 lists the autonomous mobile robot as a kind of driverless industrial truck, the category covered in Australia by AS 5144.4:2021.

The robot handles the travel: it brings an empty container to the picker, waits while items are picked into it, then carries the full container to the next zone or to the pack area. Finding and lifting items stays with the picker. Examples on this page are described by category, and no product is recommended.

How does collaborative mobile robot picking work?

A typical cycle has four steps. The warehouse management system, or a fleet manager linked to it, releases orders and assigns them to robots. A robot drives to a picker or a zone, and a screen on the robot or a handheld device tells the picker which items to take. The picker takes the item from the rack, scans or confirms it, and puts it in the robot’s tote. When the tote is complete or the picker’s part is done, the robot drives to the next zone, to a pack station or to a consolidation point.

The word collaborative describes the working relationship: people and robots share the floor and the task. It differs from a robot that works alone behind a guard. The robot travels at a controlled speed, uses sensors to detect people and obstacles, and is designed to slow or stop when something is in its path. The safety design of that behaviour is a matter for the supplier, your risk assessment and the relevant standards, which the safety and staff questions page covers.

Because the robot does not alter the racking, installation is often described as faster than systems that include fixed structure, and some warehouses add or remove robots as volume changes. Those descriptions are vendor claims. Your own timeline depends on mapping, integration, floor preparation and training.

Zone picking versus following a picker

Collaborative robots support two main working patterns, and the choice changes the numbers.

Zone picking. The warehouse is divided into zones, and each picker works in one. A robot arrives with a tote, the picker adds the items from their zone, and the robot moves on to the next zone that holds items for the order. Pickers stay in a compact area, learn it well and walk short distances. The robots do the long travel. The weak point is imbalance: if one zone has more lines than another, robots queue at the busy zone and pickers in the quiet zone wait.

Following a picker. In the second pattern the robot travels with a picker, who picks through a wider area, putting items on the robot and not walking them to a pack station. The picker still walks the pick path but stops walking back and forth to drop items. The robot is a mobile cart that takes itself away when full. It suits lower volumes and more varied work, and it saves less walking than zone picking.

Which pattern fits depends on the density of picks. A zone with many lines to pick per metre of aisle suits zone picking. A sparse, spread out range suits following better, or suggests that another method may do more good, as discussed in the goods-to-person guide.

Batch and cluster picking with robots

Picking one order at a time is rarely efficient when orders are small. Batch picking collects several orders in one pass, and cluster picking holds several order containers on one cart so the picker fills them together. Robots can carry a batch tote or a rack of order containers.

Both approaches shift work downstream. A batch tote has to be sorted into orders later, which needs a put wall, a sorter or a sorting station, and that station needs staff and space. Cluster picking avoids the second step by putting items into order containers at the point of pick, but it asks the picker to track several containers, and errors rise if the prompts are unclear.

When you test a collaborative robot system, include the sorting or consolidation step in the measurement. A gain in picking that is lost in sorting is not a gain, and some vendor figures count only the pick.

How do the robots map and navigate an existing building?

Collaborative robots navigate using sensors such as lidar and cameras, often combined with a map of the building built during setup. Some rely on markers or features in the environment, and others build the map from the shape of the walls, racking and fixed equipment. The mapping step records the aisles and the places where robots may stop. The fleet software then plans routes, avoids collisions between robots and reroutes around blocked areas.

Navigation can be affected by the environment. Racking that changes, pallets left in aisles, reflective surfaces, long uniform corridors with few features, and wrapped or shiny items near the sensors can cause problems. A change to the layout after mapping may need a remap. Ask the supplier how the robots cope with a pallet left across an aisle, how they behave if the map is wrong, and how long it takes to update the map when you change the racking.

What do the robots need from floors, aisles, Wi-Fi and charging?

Check four practical matters before any pilot. ISO’s summary of ISO 3691-4 says the condition of the operating zone has a significant effect on safe operation, and the standard has an annex on preparing that zone.

Floor. Many picking robots have small wheels and cope less well than forklifts with cracks, joins, ramps and steps. Walk the pilot zone and note slopes, thresholds, expansion joints, drains, patched concrete and anything that could stop a robot or tip a tote. Ask the supplier for tolerances and test a robot in the worst corner of the zone.

Aisles. Check aisle widths against the robot’s footprint and the room needed to pass a person or another robot. A robot that fits one aisle but cannot turn at the end will be useless. Narrow aisles can also push people and robots into close contact, which is a safety question.

Wi-Fi. Most fleets depend on wireless coverage to receive instructions, so coverage must be consistent across the whole zone, including between and behind racking. Survey the signal against the supplier’s stated requirements, with your IT team, rather than assume it. A dead spot may stall a robot at the same point every day.

Charging. Robots need charging, either during short stops at charge points or by swapping batteries. The system must plan around it so charging does not coincide with the peak. The charge points need power, space and a plan for how robots queue. Have a licensed electrician confirm power supply, and ask your insurer what conditions apply to battery charging in the building. ISO’s summary also says requirements for power sources are not covered by ISO 3691-4, so batteries and chargers need their own place in the risk assessment.

What changes for pickers and team leaders

For a picker the work becomes more concentrated. Less of the shift goes on walking, so more of it goes on picking and handling, and the pace of the work is partly set by when robots arrive. Pickers need to learn how the robot signals that it is ready, where it will stop, how to hand over a full tote and what to do when it stalls. Training should cover how to work near a moving machine, including where not to stand and how to stop it.

Team leaders take on new tasks. They watch for queues, move people between zones when imbalances appear, clear faults and decide when a robot should be removed from service. They also see data they did not have before, such as robot idle time and trips completed, and they need to know which numbers matter and when a stop needs escalating.

Consult pickers early. People who walk the aisles every day know where the floor is rough, where pallets are left and where a robot will struggle. Work health and safety law expects consultation on changes that may affect health and safety, and the safety and staff page covers what that involves.

How do you measure the pick rate you actually get?

A quoted pick rate is a vendor figure, measured under particular conditions, and it may not carry over. Measure your own, and measure it fairly.

  1. Record your baseline pick rate in lines per person-hour in the pilot zone for at least two normal weeks before the robots arrive.
  2. Run the pilot on the same products, the same shifts and the same order types, so the comparison is not distorted by an easier mix.
  3. Count all labour used by the process: pickers, team leader time on the system, sorting, error handling and robot support.
  4. Record robot availability: the share of the shift each robot is working, not charging, faulted or waiting.
  5. Record accuracy, using the same audit method before and after.
  6. Include a peak period, because the system’s behaviour at a high volume matters more than at a quiet one.
  7. Report the median and the slow days, not only the best day.

The calculator below estimates the robots needed for a peak hour from three things you can measure in a trial.

Rough robot count for a peak hour

Robot trips needed per hour 60 trips

Robots needed at peak 14 robots

Test trip times on your own layout before relying on the result, and add spare robots for faults.

Sharing aisles with people and forklifts

In many warehouses aisles carry more than pickers and robots. Forklifts replenish racking, pallet jacks move stock, and visitors and contractors pass through. Mixing these with moving robots needs planning.

Options include separating traffic by time, so replenishment happens outside picking hours; by space, with marked routes or dedicated aisles; or by controls, with robots slowing or stopping when a forklift is detected. Each has a cost. Time separation limits flexibility, space separation uses floor area and control-based separation depends on sensors and rules that must be tested.

Ask suppliers which edition of AS 5144.4 or ISO 3691-4 their robots are designed to, and for the documents that show it. A standard does not replace a site risk assessment: how your forklifts, people and robots interact in your building is for you and a qualified safety professional to assess. Check the current edition before relying on any statement about its content.

Linking robots to your warehouse management system

Robots need orders. The usual integration passes order and task information from your warehouse management system to the fleet manager and returns confirmations of completed picks. The scope of that integration matters because it determines cost, time and risk.

Ask what the system needs from your side: the format of order release, how locations are named, how inventory is updated after a pick, how short picks and exceptions are reported, and what happens if the connection drops. Ask your management system provider what they need to support the link and whether they have done it before. Include test cases in the pilot: a short pick, a cancelled order, a changed priority and a robot fault mid-order.

Data ownership is also worth settling. The robot system will generate logs of trips, faults and picks. Ask who owns them, how long they are kept, and whether you can export them to compare against your baseline without help from the supplier.

Adding robots for peak periods

One attraction of collaborative robots is scalability: you can, in principle, add robots when volume rises. Whether that works for you depends on the arrangements you can agree. Commercial terms for extra robots differ between suppliers, and this site does not describe or compare them.

Operationally, extra robots need extra charging, more space to queue, more supervision and trained staff. Adding robots to a zone that already has delays at pick faces will not speed it up; it may add congestion. Before relying on a peak plan, test the system at peak volume in the pilot, with the number of robots you intend to run.

What should you ask on a reference site visit?

If a supplier offers a visit to a customer site, treat it as research and not as a sales event. Go with a list.

  • How long did mapping and setup take, and what delayed it?
  • What was the pick rate before and after, how was it measured and over what period?
  • How many robots stop in a typical shift, why, and who clears them?
  • What did you have to change in the building?
  • How does the system behave at your peak?
  • What would you ask for differently if you started again?
  • Which products or areas did you leave out of the system, and why?

Ask the same questions of more than one site, and ask to speak to the operations manager as well as whoever arranged the visit. The pilot checklist can be used to compare what they did against what you plan, and the comparison of options helps you decide whether this is the right family for your range. Questions to the site editor can be sent through the contact form.

Frequently asked questions

Do collaborative picking robots need changes to racking?

Usually little or none, because they drive the existing aisles. They do need suitable floors, aisle width, wireless coverage and charging points. Check slopes, joins and thresholds in the pilot zone, and confirm requirements in writing with the supplier.

How do the robots know where to go?

They use sensors such as lidar and cameras with a map made during setup, and fleet software plans routes and avoids collisions. Orders come from your warehouse management system or a fleet manager linked to it. Layout changes may need a remap.

What happens when a robot meets a forklift in an aisle?

It depends on the design and on your rules. Robots are built to slow or stop when they detect an obstacle, and many sites also separate traffic by time, by space or by marked routes. Test forklift interactions in the pilot and record near misses.

Can robots be added for the Christmas peak and removed after?

Operationally, fleets can often be scaled, but commercial terms such as rental or purchase are for you to settle with a supplier. Extra robots also need charging, queue space, supervision and trained staff, so test the peak configuration during the pilot.

Do pickers need special training?

Yes. Pickers should learn how the robot signals, where it stops, how to hand over a tote, where not to stand and how to stop it in an emergency. Team leaders and maintenance staff need further training, and practice matters more than a briefing.

What Wi-Fi coverage do mobile robots need?

Most fleets need consistent coverage across the whole zone, including between and behind racking, with limits on delay and dropouts that the supplier states. Survey the signal while the warehouse is operating, with your IT team, and not from a floor plan.

How are robots charged during a shift?

Robots either charge at stations during short stops or have batteries swapped. Fleet software schedules this so charging avoids the peak. Charge points need power confirmed by a licensed electrician, space for robots to queue and a plan agreed with your insurer.